replace resource at CIF for SNP PDS

$
0
0

Hi,

since SNP done on aggregate resource level, i need to replace the resouce at CIF.

where it is better to use the user exist in ECC or in SCM (/SAPAPO/IF_EX_CURTO_SNP)?

does anyone has a sample code how it is done?

should i use method CHANGE_SNP_PDS_R3?

/SAPAPO/CURTO_SNP

• • CIF_IMPORT allows to manipulate all data after CIF-transfer.

• CALC_BUCKET_CONSUMPTION calculates the bucket capacity

consumption. /SAPAPO/CURTO_SNPDEF is a default implementation to

calculate the bucket consumption from the standard values for the duration.

• CHANGE_SNP_PDS_R3 changes the data of the SNP-PDS (from SAP

ECC)


CTM for MTO

$
0
0

Hello experts

 

The following post from 2012 says that the CTM in SNP only supports Make to Order but not Make to Stock strategy as of SCM 5.0.

CTM SNP:PL-ORD not ciffed to ECC system

 

Now that we have SCM 7.0 and many more service packs, do we still have the same issue?

Aggregated life cycle planning

$
0
0

Hi, can someone please explain the concept behind the below two check-boxes in life cycle planning? My understanding is: system is forced to consider the aggregation level mentioned in here during the forecast run i.e. consider the history at the aggregation level mentioned in here for the like profile assignments and consider the forecast to be generated at this aggregation level for the phase-in/out profile assignments.

 

But the question then is: what about the aggregation level mentioned in the background job? Is it so that it will be overridden for the maintained assignments in the life cycle table?

Capture.JPG

Thanks for your clarifications,

 

Regards,

Guru

Linking SNP PPM to desired ECC production version

$
0
0

Hi

We have a need where we manually create SNP PPMs and so the APO and ECC have no connection in terms of the PPM or production version.

I have two SNP PPM1, PPM2 in APO and I have two production versions in SAP ECC, VA and VB.

The requirement is to some how maintain a table in APO where we can choose to map the SNP PPM to ECC production version.

something like

SNP PPM1 and PPM2 both need to refer to version VB so that an SNP planned order pushed into ECC would automatically pick up production version VB.

 

Appreciate if any one can throw some light on how we can create a user maintained table or Z transaction  in APO to achieve this.

Automatic creation of SNP PPMs

$
0
0

Hi

Today we create a production version in SAP ECC that comes into APO and creates a PPDS PPM. We manually convert this into an SNP PPM.

Also when the consumptions or the operations or components change in ECC, we need to manually change the SNP PPM.

 

We are planning to automate this. We use mixed resources.

 

My question is whether any one know of an option to skip the PPDS to SNP PPM conversion and directly connect ECC master data to APO SNP PPM for automatic updates, much like the PPDS PPMs?

Forecast Horizon in Past Error

$
0
0

Hi All,

I checked the forecast horizon in past tab in snp2.once we check the forecast horizon in snp2 the demand should not show in the initial transfer in the planning book. Kindly help why the initial transfer having the demand in the planning book.

Production orders in APO getting rescheduled

$
0
0

Hi All,

 

We use SNP and so the plan orders are planned in APO and transferred to ECC. These orders are converted to Production orders in ECC and send back to APO.

 

But if there is a change in Capacity of resource (There are other unknown reasons as well) and when this capacity is reflected in APO, the production orders are getting rescheduled in APO (We dont use PPDS, but I think because the PPDS heuristics/ strategy profile is triggering automatically).

Now the production orders in ECC also reflect to the change in schedule and this is not desired by business as the schedule in ECC on those production orders were already frozen.Change in schedule is jeopardizing their plan.

 

I know this is standard behaviour in SAP but it is not suitable for our requirement. Can any one help me with a solution if you had similar issue/ requirement.

 

Any help is highly appreciated.

Setting up SNP with ECC at a macro level

$
0
0

Hello experts

 

What are the different scenarios that can be set up with SNP - ECC - SNP with respect to Distribution planning ?

Meaning stock transfers , assuming PPDS will be active and will only be used for creating PPDS planned orders.

We have 10 plants and 34 DC's and regional DC's.

 

Thank you.

Regards

KK


CTM run output

$
0
0

When we run a CTM run, what are the outputs? just demand transfer or creation of planned orders corresponding to the demand at plant too?

Example:

I have demand of 100 PCs at a DC which is sourced by two plants P1 and P2. I setup the quotas to have the plant P1 source product to DC. There is no stock at either P1 or P2.

 

I know if I run a Heuristic, the system creates just a purchase requisition at DC and purchase req. release (demand) at P1 and stops and I have to run another run at the plant P1 to generate a planned orders. I also have to deploy the stock from plant to DC in a deployment run.

 

My question is, when I run CTM, does the system just create a stock transfer at DC and purchase req. release (demand)at P1 or the system goes ahead and creates a planned order at P1 ( provided there is enough capacity at P1 resource)? Does the system deploy the product from plant to DC as well or that needs to be done through a separate deployment run?

CIF ERROR ;Address incomplete; enter country

$
0
0

Hi Experts

 

when im trying to cif Material or customer  im getting below error CIF ERROR.JPG

 

CIF ERROR ;Address incomplete; enter country

 

Please suggest ?

 

Thanks in advance

Performance issue in Demand planning

$
0
0


Hi Experts,

 

I want to know the performance factors included in Demand planning.

 

 

What is the effect of reduction in initialization period of planning area?

 

Deletion of obsolete planning version?

 

Is this feasible to delete the old data from live cache to improve performance and data storage requirement in APO?

 

Thanks & Regards,

Ankit Joshi

Total of KF Supply Shortage (BACKL)

$
0
0

Hello,

 

The stantard key figure Supply Shortage (BACKL) didn't work for its Total quantity, the aggregation and disaggregation is not defined in planning area, do you know how to get this problem resolved?

 

Thanks,

 

Mark SU

Demand Planning Add-In for Microsoft Excel

$
0
0

Hi All

 

SAP has come up with a add-in for excel in 2014. All the  documentation is available in the link SAP Advanced Planning and Optimization, Demand Planning Add-In for Microsoft Excel 1.0 – SAP Help Portal Page

 

Kindly go though the  "Administrator’s Guide" and the "Application Help" ( market place log in needed ) .The below blog is just additional screen shots /tips /tricks/ which may help consultants.The screen shots are from a test system and for actual system the security aspects like firewall settings ,HTTPS should be considered.

 

The excel add in will work only on SCM7.0 EHP3 and on higher versions of EHP2.At the client side it supports Office 2010 and higher as explained in the guide

 

1.Open the transaction SICF. The Maintain service screen opens.

2.Click the Execute button or press F8.

3.PNG

3.Expand default_host in the service list.

4.Expand sap -> scmapo -> rest-> epm.

5.Double-click demand_plan_srv. The Create/Change a Service screen opens.

2.PNG

This is only available in  SCM7.0 EHP3 and on higher versions of EHP2 ( please refer the guide )

 

6.If the service is active, you can see Service (Active) written next to the service name. If you cannot see this text displayed, continue with the next step.

7.Click the Back button.

8.Right-click demand_plan_srv in the service list.

9.Select Activate Service from the context menu that appears.

10.Choose Yes in the dialog box that opens.

1.PNG

Now test the service

 

4.PNG

 

.A new window should open with a logon screen

5.PNG

 

The Url will be in the format http://[host]:[port]/sap/scmapo/rest/epm/demand_plan_srv/

 

If the window does not appear then few ICM setting are missing in RZ10 and this has to be checked by Basis team

The three ICM seting are shown below

 

rz10_for this.PNG

 

At the client side


The excel add in  available  in marketplace and download access will be needed to get this file. It has multiple prerequisites like specific version of dotnet and MS office  as explained in the guide.

 

inst1.PNG

After installation , we can see a new add in in the excel

ex1.PNG

Click on  log on button

excel first.PNG

create a new connection for the required planning book and view as shown

pb3.PNG

 

Data in the planning book

pb1.PNG

 

Now based on the layout needed ,click the format and adjust the same

 

The row , column and page axis needs to be sent as per the requirement

fm1.PNG

 

fm2.PNG

fm3.PNG

fm4.PNG

 

 

After all this , the report should be able to pull data from planning book as shown below .

aa.PNG

If planning book numbers need to changed from excel then active the below option

edit.PNG

After this if numbers are changed in the excel and "upload data" button is clicked then numbers are changed in planning book as shown below

update data1.PNG

update data2.PNG

 

 

There are large number of options explained in the guide such as read only settings, color formatting in excel and formulas.They need to be configured as per business requirements.

 

Pros:

Most of the demand planners work in excel and will prefer to work in excel than planning book

 

 

Cons:

Supported only in SCM7EHP3 and higher versions of EHP2

Planners may expect all the data in excel and may try to avoid planning books altogether.

The impact of all the default/ start / level change /exit  macro's needs to be tested

The security aspects may be involved .If we compare this with BW-Bex report then it gives access only to read data but here it is read /write.

Performance issues with large selections need to be tested 

does anybody use Excel front end for SAP DP?

$
0
0

Hi

 

Does anybody uses excel front end that is developed by SAP for DP?  Please let me know. I like to explore it.  Thank you

Macro to change Data View into display mode

$
0
0

Hi,

 

Can any one suggest me a macro code to change a data view in Planning Book into display mode?

 

Appreciate your help.

 

Venkat.


Blocking safety stock parameters from ECC to APO

$
0
0

Hi

We have a business requirement where we need to integrate material master from ECC to APO to create the location-product master ( Standard) but block the safety stock parameters, such as safety stock, to be updated from ECC to APO.

This is so that the users can maintain the safety stock in APO instead of overwriting by ECC.

Appreciate if some body can point me to the right BADI or the code/logic.

 

Thanks

KA

MERGING MPOS

$
0
0

Hi Experts,

we have two master planning object structures for two planning areas, each for annual and monthly demand planning.

Both MPOS's have few similar characteristics and few different characteristics. Also navigation attributes may vary for each characteristics in both MPOS's. i.e the same characteristic may have navigation attribute in first MPOS and may not have navigation attribute in second MPOS.

 

Is it advisable to merge both master planning object structures into one MPOS and use it for both planning areas?

Both Planning areas may have few similar and few different key figures.

 

IF merged int one MPOS what is the impact on demand planning process?

Cyclic error in LLC determination

$
0
0

Hi Everyone,

 

We are getting Cyclic error in LLC determination, i have checked their is one one t-lane exist for that product still getting cyclic error.

scenario.

Prod: A tlane from 1 to 2.

 

when we take LLC run,we get cyclic error, how come is it possible to get cyclic error when their is only one t-lane for that source and destination.

 

 

Regards,

SA

macro vs tscopy

$
0
0

Hi experts,

i am trying to copy values from level1 keyfigure to level2 keyfigure by a macro, using a background job. But, only the values of future time bucket profile are copied and values of past timebucket profile(non editable mode) are not copied.

       If i perform /n/sapapo/tscopy, values of both past buckets and future buckets are copied.

can you please explain why this is happening.

 




Thanks & Regards

Rk

Best method of forecasting

$
0
0

I have configured my system the option of selecting 56 different methods of calculation of the forecast, but in some cases this provision does not fit reality. Articles especially true trend changing at any given time. Items that sold weekly 1 or 2 units go to sell 500 units, when I took several periods selling 500 units per week. The method that gets or is prone thereby anticipating the hit 1000 units per week because he believes it will continue to increase. Or does a very low forecast because it considers the previous periods. In this case, if only lame periods of change from the forecast will be correct, but that would force me to review items daily. It was a way to parameterize the system to have an accurate forecast of these items. Thank You

Viewing all 818 articles